Construction Schedule
31st May 2010: Unfortunately the drawings for our new school have not
yet been approved. As a result we expect the start of construction to
be delayed by 1 to 2 months.
Revised Schedule:
- Drawings sent to Department of Education for approval: 4th June 2010
- Drawings approved for tender: End June 2010
- Tender process begins: End June 2010
- Construction contract awarded: Mid Auigust 2010
- Construction begins: Mid October 2010
- Construction complete Summer 2011